Preliminary design chain for a double-girder overhead (EOT) crane — from rated load through wheel & impact loads, girder bending moment and deflection, to hoist-rope, motor and running-gear sizing.
Load & Duty
Dead Weight Components (kg)
Bridge Girder & Deflection
Hoist Rope
Motor & Running Gear
Ready to compute?
Enter your crane parameters and press Calculate Crane Design
IS 3177
Code of Practice for Electric Overhead Travelling Cranes & Gantry Cranes (other than steel works)
Duty classification, hook approach and design load conventions.
IS 807
Design, Erection & Testing of Cranes & Hoists
Structural design factors and permissible girder deflection limits.
CMAA 70
Specifications for Top Running Bridge & Gantry Multiple Girder Cranes
Impact/load factors, wheel loads and structural design of the bridge.
FEM 1.001
Rules for the Design of Hoisting Appliances
Crane group classification and dynamic (impact) coefficients.
Further Reading
Crane Classification (IS 3177)
| Class | Duty | Daily Op. Time |
|---|---|---|
| Light | I | 1 hour |
| Medium | II | 2 – 4 hours |
| Heavy | III | 4 – 8 hours |
| Very Heavy | IV | > 8 hours |
Preliminary sizing only — confirm all results against IS 3177 / IS 807 / CMAA 70 / FEM and a qualified engineer.
General guideline — always follow the governing standard.